Private retention under CIAP Document 102, and the 50% stop
On private contracts that follow CIAP Document 102, the owner retains 10% of each progress payment until half the work is done, and then stops.
- Sources read on
- Status
- Research, not legal or tax advice
The rule
Source: CIAP Document 102 (2022 edition), Article 22.02
“When fifty percent (50%) of the Contract has been accomplished, no further retention shall be made on progress billings for the balance of the Work.”
When Document 102 applies
CIAP Document 102 is the Uniform General Conditions of Contract for Private Construction. It is suppletory: it applies where a contract has no general conditions of its own, fills gaps and resolves ambiguities. Where your contract says something different, your contract governs (Foreword). The current edition was approved by CIAP Board Resolution No. 07, s. 2022, on 30 September 2022.
The same article allows not more than one progress billing a month (Article 22.02).
The billing that crosses 50%
The article is clear about billings below 50% and above it. A billing that starts below 50% and ends above it can be read two ways. The slice reading retains only on the part of the billing below 50%. The whole-billing reading retains 10% of the whole billing. The words “for the balance of the Work” favour the slice.
One billing that crosses 50%
Illustration, not tax advice- Contract price PHP 10,000,000.00.
- Billed and paid to date: 40% accomplishment.
- This billing takes accomplishment to 60%.
- VAT, recoupment and withholding are left out to show retention alone.
| Line | Slice reading (PHP) | Whole billing (PHP) |
|---|---|---|
| Work this period, 20% of the contract | 2,000,000.00 | 2,000,000.00 |
| Retention on this billing | 100,000.0010% of the 40% to 50% slice | 200,000.0010% of the whole billing |
| Paid before other deductions | 1,900,000.00 | 1,800,000.00 |
| Retention held after this billing | 500,000.00 | 600,000.00 |
Under the slice reading, retention held reaches its ceiling of PHP 500,000.00, which is 10% of the first half of the contract, or 5% of the contract price.
When retention comes back
Retention is released not later than the end of the Period of Making Good of Known Defects, when the contractor posts a Guarantee Bond, and subject to the release of liens (Articles 22.11 and 33.01). That period runs for at most 30 days after the contractor receives the last punch-list item (Article 20.12). The Guarantee Bond equals the retention released and runs for one year from posting (Article 31.05).
The document’s Schedule of Time Limits gives a different date for the same release, 60 days from substantial completion (item 3.4). Where the two differ, it is worth watching the earlier one.
Public works are different
On government projects under RA 12009, retention is 10% of the amount due before deductions until 50%. After that it stops only if the work is satisfactory and on schedule; otherwise 10% continues, and the procuring entity may reduce it to 5%. Retention is released at final acceptance (RA 12009 IRR, Section 71.2.8). Syndeo’s public-works pack, with this scheme, is planned as a later add-on.
How Syndeo handles it
- The 10% retention with the unconditional 50% stop, kept in a retention ledger per contract.In development
- The slice reading by default, printed on each progress billing, with the whole-billing reading as a contract setting. We are confirming the default with practising quantity surveyors.In development
- Release dated from Article 22.11, with an alert at the earlier Schedule of Time Limits date.In development
- The public-works retention scheme under RA 12009.Planned add-on, P2
Sources
Every source below was read on 2 October 2026.
- CIAP Document 102, Uniform General Conditions of Contract for Private Construction, 2022 edition (CIAP Board Resolution No. 07, s. 2022) (opens in a new tab)
- Implementing Rules and Regulations of RA 12009, the New Government Procurement Act, 1st edition as of 30 March 2026 (GPPB) (opens in a new tab)
Change log
- : first published.
Hear when a rule here changes
Leave your email and we will write when a page on the rules hub changes: a new issuance, a corrected reading or a new article. We have not started sending these emails yet; for now we keep your address and send nothing.