Advance payment, and how it is recouped

An advance is paid up front against a bond, then recovered from each progress billing in proportion to the work billed.

Sources read on
Status
Research, not legal or tax advice

The rule

On a private contract under CIAP Document 102, the advance is whatever amount the parties agree. The contractor posts a surety bond for the same amount, callable on demand, and the advance is recouped pro rata from the progress billings.

Source: CIAP Document 102 (2022 edition), Article 32.01

What pro rata means

Each progress billing pays back the same share of the advance as the share of the contract it bills. With a 15% advance, every billing recoups 15% of the work it bills, so the advance is fully recovered when the contract is fully billed.

A 15% advance recouped over four billings

Illustration, not tax advice
  • Contract price PHP 10,000,000.00.
  • Advance of 15%, PHP 1,500,000.00, paid at the start against a surety bond.
  • VAT, retention and withholding are left out to show recoupment alone.

On a narrow screen, scroll the table sideways to see every column.

A 15% advance recouped over four billings
BillingWork billed (PHP)Recouped, 15% (PHP)Still to recoup (PHP)
Advance paid1,500,000.00
No. 1, to 20%2,000,000.00300,000.001,200,000.00
No. 2, to 50%3,000,000.00450,000.00750,000.00
No. 3, to 80%3,000,000.00450,000.00300,000.00
No. 4, to 100%2,000,000.00300,000.000.00
Total10,000,000.001,500,000.00

Public works

On government projects under RA 12009, the advance is capped at 15% of the contract price, paid in one or two instalments against a letter of credit, a bank guarantee or a surety bond (RA 12009 IRR, Section 71.2.5). It is recouped pro rata, or, at the procuring entity’s option, progress payments are charged against the advance until it is used up (RA 12009 IRR, Section 71.2; Philippine Bidding Documents for Infrastructure, General Conditions of Contract 8.3). As the advance is repaid, the security behind it is reduced (General Conditions of Contract 8.4).

Tax on the advance is not settled

Withholding arises when a payment is paid, payable or recorded, whichever comes first (RR 12-2001, Section 4), and we found no BIR ruling on how that applies to a mobilisation advance. Some payors withhold as work is billed; others withhold on the advance and then on each billing net of recoupment. Both withhold the same total over the contract. See EWT on progress billings, and Form 2307, and take your accountant’s advice.

Why it matters for checking billings

While part of the advance is still to be recouped, the cash an owner has paid can rightly run ahead of the value certified so far. A check that ignores the advance will flag billings that are in order.

How Syndeo handles it

  • Pro rata recoupment on each progress billing, with the amount still to recoup shown on every billing.In development
  • Billing Guard allows for the advance still to be recouped, or the bond still in force, before it flags cash paid ahead of certified value.In development
  • The public-works options: the 15% cap, instalments and charging payments against the advance first.Planned add-on, P2

Sources

Every source below was read on 2 October 2026.

  1. CIAP Document 102, Uniform General Conditions of Contract for Private Construction, 2022 edition (CIAP Board Resolution No. 07, s. 2022) (opens in a new tab)
  2. Implementing Rules and Regulations of RA 12009, the New Government Procurement Act, 1st edition as of 30 March 2026 (GPPB) (opens in a new tab)
  3. Philippine Bidding Documents, Procurement of Infrastructure Projects, first edition, May 2025 (GPPB) (opens in a new tab)
  4. BIR Revenue Regulations No. 12-2001, Section 4 (opens in a new tab)