For public-works contractors
Build the SWA and the evidence as the work happens.
Public works follow different rules from private work, so they get their own pack. It is planned as a later add-on, after the private-work core. Nothing on this page is in development yet.
By role
What each role gets, and where it stands.
Public-works contractor
Build the statement of work accomplished (SWA), geotagged evidence and CPES pack as the work happens.
Planned add-on, P2Public-works finance
Government retention and withholding, including the 5% VAT withheld by government payers.
Planned add-on, P2
Nothing here is available to new customers yet: sign-ups are paused while we rebuild. Phases are explained on the product page.
Why public works need their own pack
On public works, retention continues after 50% accomplishment unless the work is satisfactory and on schedule, and the procuring entity may reduce it to 5% (RA 12009 IRR, Section 71.2.8). On private work under CIAP Document 102 it simply stops at 50% (Article 22.02).
The advance is capped at 15% of the contract price (RA 12009 IRR, Section 71.2.5), billing runs on a monthly statement of work accomplished (Section 71.2.7), and government payers withhold 5% VAT on top of the 2% EWT (NIRC Section 114(C)).
Sources read on 2 October 2026.
How we will show you
A sample pack first
When the pack is ready, we will show you a sample pack built from invented figures before you decide anything.